Case Study: Bedfordshire NTT and Amazon Data Centre Fit-out

Mechanical & Electrical Fit-out of NTT and Amazon data centre. Including cooling system, CCTV system, cage install to all RMUs and lighting. Integrated Services, extensive sector experience, a track record of delivery and a lean commercial model.

Josh Jones
Josh JonesIntergrated Services Manager
1/6/2023
Integrated Services offer an agile delivery focused alternative to traditional FM companies. Our approach combines extensive sector experience, a track record of delivery and a lean commercial model.

CASE STUDY - AT A GLANCE

Service: M&E Date Centre Fit-out
Value: £1,500,000
Start Date: August 2021
Completion: August 2022

PROJECT OVERVIEW
1-year programme of works for M&E fit-out of NTT / Amazon data centre in Bedfordshire. Our core team of 15 engineers were on-site throughout the programme, with an additional 50 engineers supporting during peak periods to match the project requirements. SCOPE OF WORKS
The works delivered included:
Cooling system
Emergency cooling system
FAP frame works
Data containment spine works
CCTV system
BMS panelling
Transformer movements
Cage install to all RMUs
Main hall and corridor lighting