Header Image
Go back

Bedfordshire NTT and Amazon Data Centre Fit-out

Mechanical & Electrical Fit-out of NTT and Amazon data centre. Including cooling system, CCTV system, cage install to all RMUs and lighting. Integrated Services, extensive sector experience, a track record of delivery and a lean commercial model.

Josh Jones
Josh JonesIntergrated Services Manager
1/6/2023
Integrated Services offer an agile delivery focused alternative to traditional FM companies. Our approach combines extensive sector experience, a track record of delivery and a lean commercial model.

CASE STUDY - AT A GLANCE

Service: M&E Date Centre Fit-out
Value: £1,500,000
Start Date: August 2021
Completion: August 2022

PROJECT OVERVIEW
1-year programme of works for M&E fit-out of NTT / Amazon data centre in Bedfordshire. Our core team of 15 engineers were on-site throughout the programme, with an additional 50 engineers supporting during peak periods to match the project requirements. SCOPE OF WORKS
The works delivered included:
Cooling system
Emergency cooling system
FAP frame works
Data containment spine works
CCTV system
BMS panelling
Transformer movements
Cage install to all RMUs
Main hall and corridor lighting

Get in touch.

Josh Jones
Josh JonesIntergrated Services Manager